& Agreements and for the Considerations aftermente’d) the sd Mr Errington | ||||
did for himself his Heirs &c covenant with the said Justices party thereto | ||||
their Extors &c that he would at his own proper Costs and Charges on or | ||||
before the sd 25th March 1780 well sufficiently and effectually build a | ||||
good and substantial Stone Bridge across the River Tyne according to the | ||||
plan thereunto annexed opposite to Hexham at a place examined and | ||||
approved by Mr Smeaton-and should procure and make the said Road and | ||||
also that sd Mr Errington his Heirs &c should and would at his and their own | ||||
proper Costs and Charges from time to time and at all times as often as need | ||||
or Occasion should be and require during the Term of 7 years uphold support | ||||
repair maintain rebuild and keep in good and sufficient Repair the said | ||||
Bridge and Road for the sd 7 years to be computed from the time that the | ||||
said Bridge and Road should have been certified for to the General Quarter | ||||
Sessions under the hands of two of His Majesty’s Justices of the peace to have | ||||
been built made finished and completed – In Consideration of the sd Mr | ||||
Errington’s Covenants and Agreements the Justices party thereto on Behalf of | ||||
the County did covenant that the Treasurer of the said County should pay Mr | ||||
Errington the sd 5,700L for the building finishing and upholding the said Bridge | ||||
and the Sum of 400L for procuring making and upholding the said Road in the | ||||
manner therein mentioned – and that Mr Errington should have take and use | ||||
as he should think fit all the Timber Stones Iron and other Materials which had | ||||
been prepared as aforesaid by the County without any payment or Satisfaction | ||||
for the same. | ||||
Mr Errington entered into and executed a Bond of the same Date with the | ||||
Articles in the penal Sum of £9,100 with a Condition for the performing and | ||||
fulfilling sd Articles | ||||
18th Geo. 3 | An Act of Parliament was passed by which sd Articles of Agreemt |
|||
were confirmed and it was amongst other things enacted that sd Bridge | ||||
when finished and completed should be deemed a County Bridge | ||||
Mr Errington in Compliance with sd Articles and to fulfil his Undertaking | ||||
set about to build the Bridge and make the Road and before the End of | ||||
January 1781 they were in all Respects finished and completed and certified | ||||
by two Justices to be built made finished and completed according to the sd | ||||
Articles and plan- | ||||
The sd Sums of 5,700L and 400L were paid to Mr Erringtons Agent, which | ||||
Sums together with a considerable Sum out of Mr Erringtons pocket (besides | ||||
the old Materials) were laid out and expended in building sd Bridge and in | ||||
pur[chas?]ing Ground for and making sd Road pursuant to sd Articles and Plan | ||||
by which Means Mr Errington was a considerable Loser by the Undertaking | ||||
11 March 1782 | By a sudden and most extraordinary Flood the Bed of the River whereon | |||
the said Bridge stood was so much affected that the Bridge was thrown down | ||||
and destroyed without any previous Appearance of any Defect and without any real | ||||
Defect in constructing or building thereof | ||||
Observations of persons eminently skilled in Works of such a Nature it is | ||||
discovered and evident that a much greater Sum of Money than what was | ||||
allowed Mr Errington will be necessary to erect another Bridge either on the | ||||
same Spot or in any other place near thereto capable of withstanding the heavy | ||||
Floods which [ |
||||
2 | ||||
Note: Draft Case to the Court of Chancery, p 2
Abbreviations are underlined like this Wm. and the expansion may be seen by moving the cursor over it.
An entry outlined like this has a note which may be seen by hovering over it. |
Transcribed by CTW and TB